Alarmed by lagging progress, a project manager chooses to crash the schedule. What is s/he doing?

Removing project activities.
Compressing the schedule deadlines by a fixed percentage.
Abandoning the established schedule and starting over.
Adding additional resources to decrease the duration of future activities.