A contract to deliver has been signed for the current project you are working on. The customer who has signed the contract has telephoned you to request additional work to be done on the project, which will affect the budget, but not the schedule of the project. What should you do next?

Respond to the customer’s request by explaining the change procedure and asking that he or she submit a request for change
Refuse the request and send a memo to your management explaining the situation
Arrange to meet with the project team to discuss this change
Do what the customer asks you to do and add the additional requirements to the original contract