There are four tasks in your project, and the duration of your current plan is 22 days. There are FS dependencies between all four tasks. Task A is four days; Task B is six days; Task C is eight days; and Task D is four days. Which of the following changes will create a Project plan with the shortest overall duration?

Create a SF dependency between Task A and Task B.
Create a FF dependency between Task A and Task D
Create a SF dependency between Task C and Task D.
Create a SF dependency between Task B and Task C.